Completed Project

Buzurgan Oil Export Pipeline

Daqing Petroleum Administrative Bureau Iraq Branch (DPABI) · Missan Oilfield, Iraq

Buzurgan Oil Export Pipeline
✓ Completed · 2013

Project Scope Summary

Overview

Scope Type: Construction & Commissioning

Provision of construction and commissioning of the Buzurgan Oil Export Pipeline Project in compliance with the requirements of DPABI. The work includes procurement, fabrication, manufacture, transportation, handling, positioning, installation, maintenance and service.

Scope

Key Work Components

  • Survey and staking, ROW cleaning and grading, construction of access roads
  • Handling, hauling and unloading of pipeline; stringing, line-up, cleaning and cold bending
  • Aligning and welding, ditching, draining, lowering-in, backfilling and tie-ins
  • Flushing, purging, gauging, hydrostatic test, pigging test and holiday test
  • Cathodic protection; road, river, channel, swale, cable and pipe crossings
  • Blasting, painting, joint coating, insulation, anti-corrosion and line markers
  • Anchor blocks, concrete slabs, balance blocks, masonry and other civil works
  • Pre-commissioning and commissioning assistance; MUSHARRAH River crossing and jacking road crossing

On Site

Project Gallery

Buzurgan Oil Export Pipeline — photo 1
Buzurgan Oil Export Pipeline — photo 2
Buzurgan Oil Export Pipeline — photo 3

Project Details

Client
Daqing Petroleum Administrative Bureau Iraq Branch (DPABI)
End User
PetroChina Iraq Limited
Location
Missan Oilfield, Iraq
Awarding Date
2013
Contract No.
DPABI/IR/JS-MS/2013-028
Project Cost
$1,862,423
Sector
Pipeline

Discuss Your Project

Get in touch with our team to discuss how Future Will can deliver your EPCC requirements.