Project Scope Summary

Overview

Scope Type: Construction & Installation of Gas Receiver Station (G.R.S)

This project involved the complete execution and handover of a Gas Receiver Station (G.R.S) as part of the 48" Abadan-Basrah Gas Pipeline Project. Future Will was responsible for all works related to construction, installation, and commissioning of the station under a unit-rate contract structure. The G.R.S. forms a critical interface in the gas transmission infrastructure from Abadan to Basrah, handling pressure regulation, gas receiving, metering and initial safety systems prior to gas injection into downstream facilities operated by SOC/ICG Group.

Scope

Key Work Components

Civil Works

  • Site clearance, grading, and excavation
  • Concrete foundations for gas station equipment
  • Cable trenches, valve pads, and pipe supports

Mechanical Installation

  • Mounting of pipeline headers and valves
  • Installation of filtration units and regulators
  • Flange assembly, leak testing, and alignment
  • Connection to 48" main pipeline system

Electrical & Instrumentation

  • Power supply to local panels and equipment
  • Instrumentation cabling for flow meters and regulators
  • Earthing and grounding works

Pre-commissioning & Handover

  • Pressure testing and nitrogen purging
  • Mechanical completion and redline drawings
  • Handover to TEGIC with operation readiness documents

Standards

Special Requirements

  • Project executed in coordination with Iranian and Iraqi stakeholders
  • Interface management with live pipeline systems
  • Tight 4-month schedule including winter working conditions
  • All work delivered to meet oil & gas HSE standards

On Site

Project Gallery

GRS Station — Abadan-Basra 48" Gas Pipeline (Shat Al-Basra) — photo 1
GRS Station — Abadan-Basra 48" Gas Pipeline (Shat Al-Basra) — photo 2
GRS Station — Abadan-Basra 48" Gas Pipeline (Shat Al-Basra) — photo 3

Project Details

Client
Tadbir Energy Gostar Iranian Company (TEGIC)
Location
Basrah, Shat Al-Basrah, Iraq
Awarding Date
2018
Contract No.
TEGI.Co./AB/C2/2018
Project Cost
$553,908
Sector
Oil & Gas

Discuss Your Project

Get in touch with our team to discuss how Future Will can deliver your EPCC requirements.

Submit Enquiry