Ongoing Project
S2/S Oil Trunkline EPCC Project
EBS Petroleum Company Limited · East Baghdad South Oilfield (EBS), Iraq

● Ongoing · 2025
Project Scope Summary
Overview
Scope Type: Turnkey EPCC – Engineering, Procurement, Construction, and Commissioning
Design, supply, construction, and commissioning of trunkline systems and associated facilities for transporting crude oil from OGMs to the Central Processing Facility (CPF), including all civil, mechanical, electrical, instrumentation, telecom, and cathodic protection works.
Scope
Key Work Components
Pipeline Construction
- 55 km of 10" to 18" API 5L trunklines (12+20+23 km) with 3LPE & FBE coatings.
- Trenching, stringing, welding, NDT (X-ray & UT), hydrotesting, nitrogen purging.
- HDD crossings for critical routes (2.7 km total).
- Installation of 3 valve stations and multiple tie-ins to OGMs and CPF.
- Internal coating for field joints using automated coating machines (robots).
Civil Works
- Foundations, pipe supports, access roads, valve pits, grading & excavation.
Cathodic Protection
- ICCP & SACP systems with test posts, anodes, rectifiers, surge diverters.
Fiber Optic Cable (FOC)
- 25 km of 24-core armored cable for SCADA and communication.
Mechanical, Instrumentation & Electrical
- Over 40 valves (2"–18"), pigging systems, pressure/temperature transmitters.
- Corrosion monitoring: coupons & probes.
- Painting & internal FBE coating with robotic systems.
Interface Works
- Tie-ins to 4 OGMs and CPF, including pressure-rated valves and integration into live systems.
Schedule
Deliverables & Milestones
| # | Description | Timeline |
|---|---|---|
| M1 | Work Start | Within 2 weeks of contract |
| M2 | Mechanical Completion | 325 days |
| M3 | Commissioning & Provisional Acceptance | 355 days |
| M4 | Final Acceptance | 365 days after M3 |
Standards
Special Requirements
- Design Standards: ASME B31.4, NACE MR0175/ISO 15156 for sour service.
- Climate Adaptation: Works in extreme summer conditions (up to 50°C) and dust storms.
- HSE & QA/QC: ISO 9001/14001/45001 standards; full compliance with Company safety policies.
- International Third-Party Inspection: SGS, BV, RINA, ATG involvement in FAT/SAT.
- Local Compliance: All materials certified by Iraqi Embassy and MOO Tech Directorate standards.
Supply Chain
Procurement Activities
- Full-scope procurement of all materials and equipment not free-issued by the Client.
- Purchase Orders signed with international manufacturers for valves (Class 300, sour service, API 6D), corrosion monitoring equipment, field joint coating systems (FBE internal, 3LPE external), fiber optic cables and cathodic protection systems.
- Expediting, QA/QC inspections, logistics, customs clearance and site delivery.
On Site
Project Gallery






Project Details
- Client
- EBS Petroleum Company Limited
- Location
- East Baghdad South Oilfield (EBS), Iraq
- Awarding Date
- 2025
- Contract No.
- 031-SC-24-EBS
- Project Cost
- $19,995,000
- Sector
- Pipeline
Discuss Your Project
Get in touch with our team to discuss how Future Will can deliver your EPCC requirements.
Submit EnquiryOther Projects
- Well Pads Construction — Eighth Batch
- GRE Pipe & Civil Construction — Water Injection Wells Tie-Ins (Y2021)
- S1 Block Oil Trunk Line & Flow Line EPCC
- Water Injection Stations EPCC — Missan
- GRS Station — Abadan-Basra 48" Gas Pipeline (Shat Al-Basra)
- Engineering & Construction of Flow Lines & Trunk Lines
- View full portfolio →