Completed Project

S1 Block Oil Trunk Line & Flow Line EPCC

EBS Petroleum Company Limited · Nahrawan, Baghdad, Iraq

S1 Block Oil Trunk Line & Flow Line EPCC
✓ Completed · 2019

Project Scope Summary

Overview

Scope Type: Design and Engineering of Flowlines & Trunklines, Civil, Anticorrosion protection, Tie-ins with existing facilities, Procurement, Construction & Commissioning

This project involved the execution of an EPCC contract for the provision of oil trunk lines and flow lines within the S1 Block area in Nahrawan, Baghdad. The scope covered detailed engineering, procurement of materials, construction, and commissioning activities, supported by full mobilization of manpower, equipment, and technical supervision.

Scope

Key Work Components

  • Detailed engineering and design of oil flow lines and trunk lines
  • Civil works and site preparation activities
  • Procurement of pipes, fittings, valves, and construction materials
  • Anti-corrosion coating and corrosion protection systems
  • Trenching, pipe laying, welding, and installation works
  • Tie-in connections with existing facilities and infrastructure
  • Mechanical completion and pre-commissioning activities
  • Commissioning, testing, and operational readiness support
  • Quality control, HSE compliance, and final project documentation

On Site

Project Gallery

S1 Block Oil Trunk Line & Flow Line EPCC — photo 1
S1 Block Oil Trunk Line & Flow Line EPCC — photo 2
S1 Block Oil Trunk Line & Flow Line EPCC — photo 3
S1 Block Oil Trunk Line & Flow Line EPCC — photo 4
S1 Block Oil Trunk Line & Flow Line EPCC — photo 5
S1 Block Oil Trunk Line & Flow Line EPCC — photo 6

Project Details

Client
EBS Petroleum Company Limited
Location
Nahrawan, Baghdad, Iraq
Awarding Date
2019
Contract No.
033/SC/19
Project Cost
$3,807,500
Sector
Pipeline