Completed Project
Engineering & Construction of Flow Lines & Trunk Lines
PetroChina International Iraq FZE · Missan Oilfield, Iraq
✓ Completed · 2018
Project Scope Summary
Overview
Scope Type: Engineering and Construction
This project involved the execution of engineering and construction works for new flow lines and trunk lines within the Missan Oilfield. The scope included full mobilization of manpower, equipment, and materials, as well as technical supervision to ensure safe and efficient implementation in line with PetroChina International Iraq FZE requirements.
Scope
Key Work Components
- Front-end and detailed engineering for flow lines and trunk lines
- Route survey and site preparation works
- Procurement of pipes, fittings, valves, and construction materials
- Trenching, pipe laying, welding, and installation activities
- Anti-corrosion coating and cathodic protection works
- Tie-in connections to existing facilities and networks
- Mechanical completion and pre-commissioning activities
- Commissioning support and system handover
- Quality control, HSE compliance, and final documentation
On Site
Project Gallery
Project Details
- Client
- PetroChina International Iraq FZE
- Location
- Missan Oilfield, Iraq
- Awarding Date
- 2018
- Contract No.
- HFY-CON/F&C0893/03
- Project Cost
- $9,292,984
- Sector
- Pipeline